2020.09 Emergency Vehicle Ramps-Forest Ave Portland

Construction Contract Info
Contractor: R.J. Grondin & Sons
Bid Amount:  $674,246.50
Projected Completion Date:  November 20, 2020

ForestAveEVR2020.jpg

Plans for Forest Ave EVR


Project Scope: The work consists of constructing Emergency Vehicle Ramps at mile 50 in Portland.
These ramps will be gated and primarily used by the Maine Turnpike Authority’s maintenance vehicles and snowplows. Other emergency vehicles such as, fire and police departments can use the ramps if needed. The work includes excavation, paving, the installation of guardrail and the maintenance of traffic.

September 2020 Update