207-871-7771 877-682-9433

2025.12 Slope & Drainage Repairs

Construction Contract Information
Contractor:
CCC Contruction LLC
Bid Amount: $266,240.00
Projected Completion Date: November 14, 2025

Culvert-at-mile-100-in-July-2025.jpg
 

Project Scope: The work for this contract includes drainage work and slope repairs for the full length of the Maine Turnpike as well as catch basin replacements. The work also includes excavation and replacing culvert pipe ends. The Authority will perform all necessary traffic control for this contract.