Construction Contract Information
Contractor: CPM Constructors, Inc., Freeport, Maine
Bid Amount: $700.000
Projected Completion Date: November 21, 2025

Project Scope: The work consists of bridge repairs at three locations. At the Beech Ridge Road Underpass in the town of York, the work generally consists of bridge curb and bridge deck coating and bridge joint seal repairs. At the New County Road Underpass in the town of Saco, the work generally consists of bridge and approach mill and overlay paving, bridge joint repairs, header installation, girder haunch removal, and miscellaneous superstructure and substructure repairs. At the Route 9/Middle Road Underpass in the town of Falmouth, the work generally consists of bridge joint repairs, header installation, and miscellaneous superstructure repairs. The work also includes maintenance of traffic and all other work incidental thereto in accordance with the Plans and Specifications.