2023.02 Exit 102 On Ramp

Construction Contract Information
Contractor: RJ Grondin & Sons

Bid Amount: $3,119,309.00
Projected Completion Date:  November 10, 2023
 
Exit102Jan23.jpg

Project Scope: The work consists of highway construction in the Town of West Gardiner, Maine at the
Exit 102 Interchange. The work includes a new southbound ramp and the removal of the existing
southbound ramp, Route 9/126 mill and overlay with shoulder reconstruction, demolition of the underpass bridge, pavement, signing, guardrail, highway lighting, and maintenance of traffic.

November 2023 Update

October 2023 Update

August 2023 Update

July 2023 Update

June 2023 Update

May 2023 Update

April 2023 Update

March 2023 Update

February 2023 Update

January 2023 Update