2024.09 York Vehicle Storage

Construction Contract Information
Contractor:
Optimum Construction Inc.      
Bid Amount: $2,228,630.39
Projected Completion Date: October 3, 2025

Crews-construct-bollards-at-York-Maintenance-in-August-2024.jpg

Project Scope: The work consists of the following:
            1. Construction of an approximate 6,600 square foot pre-engineered building consisting of six (6) equipment storage garage bays.
 
            2. All site work, paved parking and facility operation areas, and site utilities.
 
The work includes all building structure, mechanical, electrical, and plumbing, as well as all site work, grading, pavement, lighting, and utilities.
 

January 2024 Update

December 2024 Update

November 2024 Update

October 2024 Update

September 2024 Update