207-871-7771 877-682-9433

2024.03 Clearzone and Drainage Improvements MM 20.0 TO MM 23.3

Construction Contract Information
Contractor: 
Pike Industries, Inc.                 
Bid Amount: $7,075,386.13
Projected Completion Date: August 30, 2024

Turnpike pavement
Project Scope: The pavement rehabilitation work consists of milling the shoulders northbound and southbound and paving them to match the existing one inch overlay from Mile 20.0 to Mile 23.3. The full width section will then receive an inch and a half overlay. Excess material in the median will be removed to restore proper drainage, catch basins will be rebuilt and adjusted as necessary. Guardrail work, temporary pavement markings, maintenance of traffic.

July 2024 Update

June 2024 Update

May 2024 Update

April 2024 Update