2022.06 Superstructure Replacement - Route 197 Bridge

Construction Contract Information
Contractor: 
Scott Construction Corporation
Bid Amount: $2,988,608.00
Projected Completion Date: October 28, 2022 By end of December 2022 (to be open through winter - will need to close again in spring for final pavement treatment)
 
Route-197-Bridge.png


Project Scope: The work consists of replacing the Richmond Road (Route 197) bridge superstructure over the Maine Turnpike in the Town of Litchfield, Maine. The work includes concrete deck, steel girder and bearing replacement, concrete substructure modifications and repairs, approach work and paving, guardrail, bridge rails and maintenance of traffic. 
 