2019.15 Gray Service Plaza Fuel System Replacement


Construction Contract Info
Contractor: SRS Petroleum Services
Bid Amount: $1,721,439.00
Projected Completion Date: June 19, 2020
 
GraySerivceplazafuelOct2019.jpg



Project Scope: The work consists of removing and replacing the underground gas and diesel storage tanks at the northbound travel plaza in Gray, providing final installation of temporary gas and diesel dispensers using above ground storage tanks, associated electrical, mechanical, drainage, site work and maintenance of traffic.


September 2020 Update

July 2020 Update

June 2020 Update