2021.03 Northern Bridge Repairs

Construction Contract Info
Contractor: CPM Constructors, Inc
Bid Amount: $1,298,652.20
Projected Completion Date:  November 30, 2021
 
Route-9-bridge-photo-(2).png
Route 9 Underpass Bridge, Sabattus
 

Project Scope:  This project includes repairs to three bridges on the Maine Turnpike in the municipalities of New Gloucester and Sabattus. Below is a description of the work at each location.

Bennett Road Underpass Bridge, New Gloucester - The work consists of general repairs and modifications to the Bennett Road Underpass Bridge at Mile 68.6 in New Gloucester.  The work includes pavement and membrane replacement, end of deck and backwall reconstruction, concrete repairs, pavement grinding and overlay on the approaches.  In order to complete this work, the bridge will be closed for approximately two months beginning on June 21, 2021. 

Grove Street Underpass Bridge, Sabattus - The work on the Grove Street Underpass Bridge at Mile 83.7 in Sabattus consists of beam repairs due to a bridge hit that occurred in 2020. In order to complete this work, the bridge will be closed for approximately 60 days.  

Route 9 Underpass Bridge, Sabattus - The work consists of general repairs and modifications to the Route 9 Underpass Bridge at Mile 86.1 in Sabattus.  The work includes pavement and membrane replacement, bridge joint repairs and modifications, concrete repairs, and pavement grinding and overlay of the approaches.  The bridge will remain open to traffic during the repairs utilizing a temporary traffic light to allow for alternating one way traffic. The alternating one way traffic pattern will be in place until early October 2021.

 

February 2022 Update

January 2022 Update

November 2021 Update

August 2021 Update

July 2021 Update